Skip to Main Content

Planned Maintenance

As you may be aware, we have recently completed phase 2 of the Planned Maintenance programme. Please see below a breakdown of the installations completed during phase 1 and 2 of the works.

 

CCG (Campbell Construction Group) Installations

Phase 1

Phase 2

Total

 

Amount of  Properties with Boiler Replacement Works

99

94

193

 

Amount of Properties with Bathroom Replacement Works

75

91

166

 

Amount of Properties with Kitchen Replacement Works

118

147

265

 

Amount of Properties with Window Replacement Works

2

19

21

 

 

A number of tenants refused to have the works carried out for various reasons, however, still have the opportunity to contact us on 0141 959 2552 if they wish to be added back into the programme.

 

Phase 3 of the programme will be commencing shortly. The contractor will make contact with each tenant in this phase to carry out a survey prior to the works commencing. They will also provide a confirmation of the start date at least 10 days prior to the installation date. It is essential that you contact the Contractor on the telephone number provided in the letter if the installation date does not suit you, as it is CCG that co-ordinates the programme, not the Association.

 

There will be 110 properties receiving upgrades during phase 3, please find below breakdown of the quantity of each component being replaced:

 

 

Phase 3

Total Number of Properties Available to Install

110

Amount of  Properties with Boiler Replacement Works

20

Amount of Properties with Bathroom Replacement Works

51

Amount of Properties with Kitchen Replacement Works

107

Amount of Properties with Window Replacement Works

27

 

If you have any queries about the planned works, please contact David McCormack, Property Services Officer.

 We Are A Living Wage Employer LogoLogo OscrLogo Glasgow Living EmployerLogo Scottish Housing RegulatorLogo scottish housing network   Logo Gwsf.  logo share.  logo social housing safetylogo SFHA